EPA Announces Cleanup Plan For Troubled Missouri Landfill

Some of the nuclear waste buried near a smoldering underground fire at a Missouri landfill will be dug up and the rest will be capped under a new federal plan.

The U.S. Environmental Protection Agency's remedy announced Thursday comes a decade after its initial cap-and-monitor proposal at suburban St. Louis' West Lake Landfill was met with so much opposition that the agency went back to the drawing board. The partial excavation plan slightly modifies a proposal announced in February.

The project is expected to take a little over four years and cost $205 million, a price tag to be shouldered by the landfill's owner and other parties deemed responsible for the contamination.

Bridgeton Landfill favored capping the site and says in a statement that partial excavation creates unnecessary risks.

The Associated Press is one of the largest and most trusted sources of independent newsgathering, supplying a steady stream of news to its members, international subscribers and commercial customers. AP is neither privately owned nor government-funded; instead, it's a not-for-profit news cooperative owned by its American newspaper and broadcast members.